A cloud migration is a programme that runs long enough for its own assumptions to expire. The teams that come through it cleanly share a pattern: they invest heavily in assessment, they build a landing zone that encodes their guardrails before anything moves, and they migrate in waves that each end with something decommissioned on the other side. Everything else is detail — expensive detail, but detail.
Phase 1 — Assess: the inventory that plans the programme
Assessment is where migration programmes earn their outcomes. The goal is not a complete CMDB; it is a decision-ready view of every application: what it does, what it depends on, who owns it, what it costs to run today, and which of the 7 Rs it should take. Automate discovery where you can — dependency mapping tools earn their cost quickly — but expect a manual pass for the awkward systems no scanner understands.
- Application inventory with business owner, criticality tier and current run cost
- Dependency map — the synchronous calls and shared databases that determine migration order
- Constraint register — compliance, licensing, latency and contractual obligations per workload
- Rationale per application for its 7R classification, reviewed with the application owner
Automated dependency mapping earns its cost quickly, but every technique sees only part of the truth. Flow-log analysis shows the network conversations your tooling can attribute, and misses the batch job that fires on the last working day of the month. Runtime agents capture process-level connections — including the ones nobody documented — but only where they are deployed. CMDB records and firewall rule reviews surface the shared services every application quietly leans on: DNS, NTP, directory, monitoring, backup and the security agents that phone home from every host. Reconcile all three, then validate the map in workshops with the people who get paged: draw it on a wall and let them correct it. The dependencies that break migrations are almost always intermittent or shared — the month-end batch, the reporting tool that reads production databases directly, the service account used by four systems at once. Organise the workshop around those questions, not around the diagram.
The 7 Rs — with decision criteria, not definitions
| Strategy | When it fits | Watch out for |
|---|---|---|
| Rehost (lift & shift) | Speed matters, little time to refactor, first wave | Carrying on-premises inefficiency into a cloud invoice |
| Replatform (light optimisation) | Managed services remove real operational load cheaply | Scope creep into full rewrites mid-wave |
| Repurchase (move to SaaS) | Commodity capability a product already does better | Data migration and integration effort |
| Refactor (re-architect) | Cloud-native value justifies the investment | Underestimated engineering effort; do it after the landing zone proves itself |
| Retire | Unused or redundant systems | Silent dependents nobody documented |
| Retain | Constraints make migration unwise for now | Becoming permanent by default — set a review date |
| Relocate | Hypervisor estate moves with minimal change | Licensing implications on the new platform |
Each strategy has a characteristic shape in practice. Concrete examples make the classification faster and less political:
- Rehost: an internal reporting platform of a dozen VMs with no roadmap and a hosting contract running out. Moving it unchanged beats optimising something scheduled for replacement.
- Replatform: a Java application on hand-built VMs that becomes containers over a managed database — the code survives, most of the operational burden does not.
- Repurchase: an on-premises ticketing system where a SaaS product already covers the requirement and the integration surface is small enough to rebuild quickly.
- Refactor: a customer-facing order pipeline where elasticity and release speed justify re-architecting — funded like a product, scheduled last, and measured against the value it unlocks.
- Retire: the departmental file share nobody remembered, discovered in assessment and switched off with its owner's agreement — the cheapest migration there is.
- Retain: the manufacturing execution system tied to shop-floor hardware, kept in place with a documented review date and a compensating integration to the cloud estate.
- Relocate: a hypervisor estate moving to a cloud-based hypervisor service when licensing and operations make lift-and-shift unattractive but re-platforming unjustifiable.
Phase 2 — Mobilise: build the landing zone first
The landing zone is the platform your migrated workloads land on: account structure, networking, identity, logging, security guardrails and cost allocation. Building it before wave one is the single highest-leverage decision in the programme — retrofitting guardrails onto 200 migrated workloads costs an order of magnitude more than defining them upfront.
- Account or subscription structure with clear ownership boundaries
- Identity federation and least-privilege roles before any workload arrives
- Network topology: hub-and-spoke or shared services, with egress paths designed
- Policy-as-code guardrails for security, tagging and region restrictions
- Centralised logging, monitoring and cost allocation wired to teams
- A landing zone that passes a security review before the first wave starts
Phase 3 — Migrate in waves that each deliver value
Waves are the programme's heartbeat: a batch of applications, migrated, verified and handed to operations — with the old environment decommissioned. Size waves to your team's capacity, not to a deadline slide. A common and effective ordering: low-risk internal applications first (to learn the platform), then stateless workloads, then stateful and integrated systems, with the most complex refactor candidates last — or never.
-
01
Plan the wave
Select applications with their dependencies in the same wave — split dependencies are how cutover weekends become cutover quarters.
-
02
Migrate & validate
Infrastructure as code, automated testing against acceptance criteria, performance baselines compared to on-premises.
-
03
Cut over with a rollback
Every cutover plan names its rollback trigger, its owner and its decision deadline. Practice the rollback before the cutover.
-
04
Decommission & review
Retire the old environment, capture the actual run cost, and feed lessons into the next wave plan.
Cutover planning
A cutover plan is a timed script with named owners, not a calendar invite. Write it as an ordered sequence with expected durations, verification points and explicit go/no-go decision times — a cutover without decision deadlines drifts until the only remaining options are "push on" and "explain why we stopped". Rehearse it at least once, on a lower environment or a reduced replica: a dress rehearsal surfaces sequencing errors, missing access rights and unclear ownership while they are still cheap to fix.
- Timed runbook with a named owner for every step and a single cutover lead who owns the decisions
- Go/no-go decision points at fixed times, with criteria agreed before the window opens
- Data synchronisation plan: the final delta, its window, its verification, and who confirms it
- Communication plan: who is told what and when — including the business stakeholders waiting on the result
- Rollback trigger, rollback owner and decision deadline, agreed before the cutover starts
- Verification suite ready to run: functional checks, performance smoke tests and integration probes
- Change freeze on both environments for the duration of the cutover window
- Heightened monitoring and alerting for the first 48 hours, with named responders
Rollback strategy: decide before you start
A rollback you have not rehearsed is a hope, not a strategy. Set the trigger thresholds and the decision owner before the cutover window opens, and be explicit about the asymmetry: a rollback that would lose writes or discard migrated data is not a rollback but a different forward plan. Where the data migration is one-way, say so in the runbook and define what a forward fix looks like instead. The decision belongs to the cutover lead and must be taken at the decision deadline — decisions made by exhausted teams at four in the morning optimise for sunk cost, which is how cutover weekends become cutover weeks.
The migration factory: an operating model for many waves
Programmes moving more than a handful of applications run better as a factory than as a project: a standing team with a standard process, taking applications in through one intake queue and delivering them migrated, tested and decommissioned. The alternative — every application team migrating itself with shared consultants — repeats the learning curve per team and leaves the landing-zone standards brittle. The factory is not bureaucracy; it is how the lessons of wave one reach wave seven.
- Intake — a single entry point that validates readiness: named owner, dependencies mapped, 7R agreed, test plan exists. Applications that fail intake wait; they do not enter a wave.
- Platform workstream — owns the landing zone, the guardrails and the paved road: pipeline templates, infrastructure-as-code modules, monitoring baselines.
- Migration workstreams — small, stable teams that take one wave at a time and carry their lessons into the next wave's plan.
- Factory metrics — throughput per wave, first-time-right rate, decommissioned capacity and open risks. Review them the way a production line reviews defects.
Stakeholders: communicate in their currency
Migration programmes are visible to people who do not care about landing zones. Business owners need to know when their systems freeze and what changes for their users; application owners need dates, test expectations and a real escalation path; sponsors need scope, wave progress, retired capacity and the top risks on one page. Give each audience its own cadence — a weekly one-pager for sponsors, wave kick-offs and cutover notices for application teams, end-user communication timed to what actually changes for them. The failure mode is silence: teams that communicate only when asked spend their credibility at exactly the moment cutover anxiety peaks.
Phase 4 — Operate: steady state and the cost reality
The business case rarely survives contact with the first invoice — not because it was wrong, but because it modelled consumption and forgot the rest: data transfer, non-production environments, support tiers, tooling, and the platform team required to run it all. Build the cost model before the first wave, and treat FinOps as a migration deliverable, not a later project. Our cloud cost optimization guide covers the operating practices in depth.
The post-migration review
Run a review after every wave, while the memory is fresh and before the next wave plan hardens. Compare actuals against plan on the four numbers that matter — elapsed time, cost to migrate, steady-state run cost and defects in the first thirty days — and write down what surprised you. Then turn each surprise into a change: to the intake criteria, the landing zone, the wave sizing or the estimating model. Programmes that do this visibly converge after two or three waves; programmes that do not repeat the same lessons at higher volume. At programme end, the benefits review compares retired capacity and actual run costs against the business case — which is what determines whether the next migration gets funded on the same terms.
The end state worth aiming for is unglamorous: migrated workloads on a governed landing zone, an operations team that knows the platform, cost allocation that shows every team its own spend, and a decommissioned data centre. That outcome is achievable in most programmes — provided the sequencing holds and the wave discipline survives the inevitable schedule pressure.
Frequently asked questions
What order should we migrate applications in?
Start with low-risk internal applications to learn the platform, then move dependency clusters together — never split tightly coupled systems across waves. Leave refactor-heavy, business-critical systems for later waves once the landing zone and team are proven.
How do we estimate migration cost realistically?
Model four buckets: migration execution (tooling, professional services, engineering time), parallel running (double infrastructure and licensing during transition), steady-state run cost on the new platform, and the platform team required to operate it. Then add a contingency for the systems the inventory missed.
What is a landing zone and why does it matter?
A landing zone is the standardised foundation your workloads migrate onto: account structure, networking, identity, security guardrails, logging and cost allocation. Defining it before migration means every workload inherits your controls automatically; retrofitting it later means touching every migrated application.
Should we migrate everything at once?
No — big-bang migrations concentrate every risk into one weekend. Wave-based migration keeps each batch small enough to verify, roll back and learn from. The exception is small estates with few dependencies, where the overhead of many waves can exceed the risk of one.
How detailed should a cutover plan be?
Detailed enough that someone outside the migration team could execute it: every step timed, owned and verifiable, with explicit go/no-go decision points and a rollback decision made before the window opens. Rehearse it at least once. Plans that live only in the team's heads fail at the first surprise at two in the morning.
- Migration
- 7 Rs
- Landing zone
- Wave planning
- Assessment
Was this guide useful?
Keep reading
Related resources
Cloud Platforms
How to Choose a Cloud Platform in 2026: A Decision Framework
A practical framework for choosing between AWS, Azure and Google Cloud — constraints, scoring, three-year TCO, pilot design and the decision traps to avoid.
Cost Optimization (FinOps)
Cloud Cost Optimization: A Practical FinOps Playbook
A practical FinOps playbook for cloud cost optimization: allocation, rightsizing, commitments, storage hygiene, unit economics and the operating cadence that keeps savings.
Cloud Security & Compliance
Cloud Security Best Practices: Identity, Posture and Defence in Depth
Practical cloud security best practices: shared responsibility mapped to services, identity-first architecture, posture management, data protection and audit-ready evidence.